The cost of last year’s Olympic and Paralympic Games in Rio de Janeiro has increased to BRL$43.3 billion ©Getty Images

The cost of last year’s Olympic and Paralympic Games in Rio de Janeiro has increased to BRL$43.3 billion (£10.4 billion/$13.2 billion/€11.8 billion) - around BRL$14.5 billion (£3.5 billion/$4.4 billion/€3.9 billion) more than originally planned.

This is according to figures published in a report by the Governing Authority of the Olympic Legacy (AGLO).

The report was initially due to be released in February, with updates coming every six months after the Games.

The publication was delayed, however.

The original budget when Brazil won the hosting rights to the Games in 2009 was BRL$28.8 billion (£6.9 billion/$8.8 billion/€7.8 billion).

The total cost announced by AGLO, which said BRL$7.23 billion (£1.73 billion/$2.21 billion/€1.98 billion) was spent on venues for the Games, may still increase further.

Globo Esporte reports that the cost of infrastructure projects increased to BRL$26.7 billion (£6.4 billion/$8.2 billion/€7.3 billion) and another BRL$9.2 billion (£2.2 billion/$2.8 billion/€2.5 billion) was spent on operating costs.

Rio 2016 had an initial operational budget of BRL$8.7 billion (£2.1 billion/$2.7 billion/€2.4 billion), with communications director Mario Andrada telling insidethegames in April that he estimated around one per cent remained.

It was revealed in April that Rio 2016 owe BRL$87 million (£20.8 million/$26.6 million/€23.8 million) in outstanding payments to suppliers and third parties.

A plan for the future use of Olympic venues was also expected to be announced by the AGLO.

Reports say AGLO President Paulo Marcio Dias Mello spoke vaguely about this matter, but he did not provide any cost or income figures.

The total cost of the Rio 2016 could still rise further ©Getty Images
The total cost of the Rio 2016 could still rise further ©Getty Images

There has been some limited progress recently in the efforts to fulfil other parts of the Rio 2016 legacy.

Rio City Hall officially opened Carioca Arena 3, one of the venues used last year in the Olympic Park at Barra de Tijuca, to the Brazilian public last month.

The venue staged taekwondo and fencing competitions at Rio 2016, before hosting judo and wheelchair fencing at the Paralympic Games.

Badminton, table tennis and trampolining are set to be among sports housed in the venue for public use.

Part of the Barra da Tijuca Olympic Park was opened to the public in January, with the Via Olímpica now used for skating rinks, multi-sport courts and a series of other sporting activities.

A section of the Deodoro Olympic Park was returned to the military and is being used by them and is also being used as the Brazilian Olympic Committee's training centre.

The area of the Park containing the BMX and canoe slalom venues was closed in January when a management contract came to an end, although it is claimed it could open again by the end of June following a tender process.

Prosecutor Leandro Mitidieri, presenting at an AGLO meeting last month, delivered a highly critical assessment of the Olympic legacy.

He claimed the city of Rio de Janeiro had failed to plan for the transfer of key venues, including the Olympic Velodrome, Tennis Centre and Carioca Arenas 1 and 2.

A public bidding process was reportedly set to take place, but Mitidieri claimed this had failed and venues were passed to the Brazilian Government without any plan.

Marcio Dias Mello said "it's not easy to manage the legacy".

"London, for example, took two years to deliver the legacy [after the 2012 Olympic Games] and even today there is public investment in that legacy," he added.

"Even if it doesn't meet everyone's expectations, it will be a relief that what we have here will not be white elephants."

The IOC do not seem too worried about how much Rio 2016 cost, claiming that a lot of improvements in the city would not have been possible without the Olympics ©Getty Images
The IOC do not seem too worried about how much Rio 2016 cost, claiming that a lot of improvements in the city would not have been possible without the Olympics ©Getty Images

The IOC, however, claim they were not concerned by the report. 

They said the budget, as set out by the Rio 2016 Organising Committee in 2009, was $2.8 billion (2.2 billion/€2.5 billion) and they were "reassured" that this is still "in line" with what was proposed at the time of the Games being awarded to the city.

The statement also said the investments made into infrastructure will benefit the people of Rio for many years and that these costs should not be included into the overall costs of the Games.

"The IOC made a huge contribution to support the staging of these Olympic Games," the statement said.

"This included the commitment of $1.5 billion (£1.2 billion/€1.3 billion) and an exceptional effort to find cost savings and additional financial contributions by all Olympic stakeholders, to make these historic Games possible. 

"On top of this, Rio 2016 was also able to take advantage of very considerable marketing revenues. 

"All of this would not have happened without the Games.

"Rio 2016 provided the opportunity to Rio to bring forward a number of long-term investment projects, many of which were not directly related to the staging of the Olympic Games.

"This infrastructure budget was under the scope of the Government authorities and included the metro, new bus lines, the revitalised harbour, the clean-up of the Guanabara Bay and other projects which directly benefit the people of Rio. 

"It simply does not make sense to include these infrastructure investments which will provide long term benefit to the city and the region in the cost of the Games."

The IOC went onto say that officials in charge of the Games' legacy must maintain promises to make the investments "bear fruit for the general public".

"When the right efforts are made, we already see good examples – the Maria Lenk Aquatic Park continues to have regular training and competition action as a part of Team Brazil Training Center, which receives over 200 athletes from 12 different Olympic disciplines," the IOC said.

"Several venues are operational, as seen at Carioca 3 and the gymnastics arenas; the city has its first public golf course, open to all. 

"We hope that these cases will act as an example for the remaining challenges and that they will particularly encourage the public authorities to deliver on the commitments for a strong legacy. 

"This is in particular true for the Future Arena [handball] which was promised to be turned into four public schools."